Aging electricity grids, energy losses and outages are keeping Uzbekistan from fully using a 50% rise in power plant capacity, the Central Bank said in a draft concept on the main directions of monetary policy for 2027-2029.
Installed capacity rose 50% in 2021-2025, helped by new energy facilities and wider use of renewable sources, the report said. But equipment wear, technical losses and grid capacity limits can stop power reaching consumers even when generation is sufficient.
Official data show about 4,000 grid accidents in June-July 2026, with power losses estimated at 17.2%. It was reported at a meeting chaired by the president on July 27 that residents and businesses in some provinces had been left without electricity for 8-10 hours, and that losses reached 4.8 billion kilowatt-hours over six months.
The Central Bank described reliable power supply as a factor in a sustained fall in inflation. Outages can halt production and raise costs, adding to price pressure if output lags demand. It warned that repeated outages and further price rises driven by higher tariffs could require tight monetary policy, and therefore high interest rates, to stay in place longer. Its baseline forecast sees inflation falling to 5% in the second half of 2027.
Moving tariffs closer to economically justified levels creates financial conditions for renewing the sector but raises costs for households and businesses, the bank said. It argued that increases should come with better service, lower technological losses and more efficient management, and has proposed announcing a tariff schedule several years ahead.
The World Bank estimates Uzbekistan will need about $3 billion by 2030 to modernize and expand distribution grids. In October 2026 it announced financing for a $371 million program to modernize and digitize 60 key substations nationwide, with $200 million from the Asian Development Bank, $100 million from the World Bank and $71 million from Uzbekistan. The upgrade is expected to cut annual losses at the substations by 20,000 MWh and allow connection of an extra 3.3 GW of renewable capacity by 2031.
President Shavkat Mirziyoyev said on Feb. 23, 2026, that without additional trunk lines, power plants’ output could exceed grid capacity, and that spending of funds allocated in 2025 for grid development had been too slow. Planned measures include three high-voltage lines totaling 602 km.
The World Bank said in May 2025 that more than half of Uzbekistan’s distribution grid assets had been in service for over 30 years, and put technical losses in distribution networks at about 13% in 2024. About 30 trillion soums has gone into modernizing electricity and gas networks over the past decade.