Afghanistan's National Development Corporation said Wednesday that construction of the Qosh Tepa Canal in the country's north had entered its final stage and that it would soon begin receiving water from the Amu Darya.
"Construction work on Qosh Tepa, a major national canal, has reached its final stage," the corporation said in a video report. "Plans are in place to let water from the Amu Darya flow into the canal through the main intake structure soon."
Work on the second phase is 99% complete, the corporation said, according to Safir television. Spokesperson Nabiullah Arghandiwal said water would be directed into the canal soon after the intake structure was built.
The timing contrasts with remarks by Uzbekistan's Water Resources Minister Shavkat Khamraev, who told a news conference on Nov. 19 that the canal would not take water from the Amu Darya before 2030. He said the volume drawn in low-water years would be a subject of negotiations with Afghanistan.
Afghanistan has not joined Central Asian states' agreements on transboundary waters. The Taliban authorities' lack of international recognition also complicates the conclusion of treaties with Kabul.
Earlier reports said excavation in the second phase was nearly finished, with bridges and water control structures under construction. Once the work is complete, water is expected to reach Andkhoy district in Faryab province.
Background
The Taliban returned to power in August 2021 and began building the canal in 2022. The roughly 285-km waterway is designed to irrigate nearly 550,000 hectares in Balkh, Jawzjan and Faryab provinces. Water was observed in its first section in 2023. According to Uzcosmos, it began flowing along the channel that October after temporary barriers were removed.