Construction of the second stage of the Yunusabad line of Tashkent underground, for 2017-2019 , is estimated to cost 124.8 million US dollars. The estimated cost of the project is given in the Presidential Decree, approved in November and published on the Finance Ministry’s website on January 4.
The project will be financed through the state budget funds totalling 72 million US dollars in equal installments over three years, and the 52.8 million dollar loan of the Reconstruction and Development Fund.
Foreign experts will be engaged for the examination of project documentation, quality assurance and control, and technical supervision over construction works, if necessary, also over specialized construction and installation works.
The cost of unfinished facilities within the project with overevaluation as of October 1, 2016 is 6.91 billion soums.